EVM Demo · Hotel renovation

Earned Value, one decision at a time

10 rooms × $1,000 each. Budget at completion (BAC) = $10,000. Only finished, accepted rooms earn value.

▶ Today: end of week 2 of 6 · 33% of the time used

W1 ✓
plan 2
W2 ◀ now
plan 2
W3
plan 2
W4
plan 2
W5
plan 1
W6
plan 1

Work done: 3 of 10 rooms (30%) · plan by now: 4 (40%)

Money spent so far: $3,500

■ finished (100%) · ▢ should be finished by now but isn't (0%) · ▢ not due yet

Rooms only count as earned when fully finished — no partial credit.

End of week 2

The plan said 4 rooms by now (planned spend $4,000). The team finished 3 rooms and spent $3,500.

Does spending less than planned mean we're performing well?